Delhi Pollution Control Committee

Government of NCT of Delhi

Deciding Authority & Timeline for disposal of Consent / Authorization

  • Home
  • CONSENT
  • Deciding Authority & Timeline for disposal of Consent / Authorization

Deciding Authority & Timeline for disposal of Consent / Authorization

In accordance with the directions issued by the Nodal Agency, closure action is being taken against the following industries, in Group 'F' in the Master Plan, which are undisputedly polluting industries. No industry falling in these categories are allowed to operate in non-conforming areas.
Type Consent For Category * Timeline Documents Required Procedure Deciding Authority
Green CTE (Consent to Establish) Form
I
7 days Cell In-charge /SEE
Green CTO (Consent to Operate) Form
I
7 days Cell In-charge /SEE
Green CTO(R) (Consent to Operate (renewal)) Form
I
7 days Cell In-charge /SEE
Orange CTE (Consent to Establish) Form
I
7 days Cell In-charge /SEE
Orange CTO (Consent to Operate) Form
I

7 days

Cell In-charge /SEE
Orange CTO(R) (Consent to Operate (renewal)) Form
I
7 days Cell In-charge /SEE
Orange CTE (Consent to Establish) Form
II(a)
30 days Committee headed by Charman
Orange CTO (Consent to Operate) Form
II(a)
30 days Committee headed by Chairman
Orange CTO(R) (Consent to Operate (renewal)) Form

II(a)

30 days Committee headed by Chairman
Orange CTE (Consent to Establish) Form

II(b)

30 days Committee headed by MS
Orange CTO (Consent to Operate) Form
II(b)
30 days Committee headed by MS
Orange CTO(R) (Consent to Operate (renewal)) Form
II(b)
30 days Committee headed by MS
Authorization under Hazardous and Other Wastes (Management and Transboundary Movement) Rules, 2016 Form
II(a)
30 days Committee headed by Chairman
Authorization under Hazardous and Other Wastes (Management and Transboundary Movement) Rules, 2016 Form
II(b)
30 days Committee headed by MS

Authorization under HWM Rules will be decided, along with consent application, with the time period specified against said of the item above.

* Category I - which do not require installation of pollution control device(s) such as Emission Control System (ECS) or Effluent Treatment Plant (ETP) / Sewage Treatment Plant(STP)

* Category II - which require installation of pollution control device(s) for controlling pollution in emission / effluent

(a) SPIs /STPs of DJB,WTPs of DJB,CETPs / Power Plants / MSW Plants etc.

(b) Other than those falling under clause (a).

Note : For more details such as deciding authority,time frame for disposal etc may please see office order dated 12.04.2016